Copy Baseline : Absolute no. shall also be copied as the baseline version

Hi,

I have observed that while Copying Baseline using File-> Baseline -> Copy the Absolute no.\ID for the copy would start from the no. specified and would run in sequence. But is there a way to copy the existing absolute no.\ID of the baseline version itself.
DXLScripter - Fri Aug 24 07:39:41 EDT 2012

Re: Copy Baseline : Absolute no. shall also be copied as the baseline version
SystemAdmin - Fri Aug 24 07:46:18 EDT 2012

Hi,

see e.g. http://www.ibm.com/developerworks/forums/thread.jspa?messageID=14385645

Regards
Mike